<?xml version="1.0" encoding="UTF-8"?>
<!DOCTYPE article PUBLIC "-//NLM//DTD JATS (Z39.96) Article Authoring DTD v1.4 20240229//EN" "JATS-articleauthoring1.dtd">
<article article-type="research-article" xml:lang="zh-CN" xmlns:xlink="http://www.w3.org/1999/xlink">
  <front>
    <journal-meta>
      <journal-id journal-id-type="publisher-id">58</journal-id>
      <journal-title-group>
        <journal-title>施工技术研究</journal-title>
        <abbrev-journal-title>Research on Construction Technology</abbrev-journal-title>
      </journal-title-group>
      <issn>ISSN: 3104-8129 EISSN: 3104-8137</issn>
      <publisher>
        <publisher-name>睿核出版社有限公司</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.65700/RHSGJSYJ01-2611-8129-0564</article-id>
      <article-id pub-id-type="publisher-id">17346</article-id>
      <title-group>
        <article-title>基于 BIM 技术的配电网工程施工进度动态管理策略</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>彭晖深</string-name>
        </contrib>
      </contrib-group>
      <pub-date pub-type="epub">
        <year>2026</year>
        <month>3</month>
      </pub-date>
      <issue>3</issue>
      <abstract>
        <p>配电网工程建设量大面广、时间紧迫、外部环境复杂、多个单位同时施工，传统的用横道图以及人工例会对施工进度进行管理
的方式，在信息传递、偏差发现及及时纠正上都有较大时滞，不能满足配电网建设日益发展和精细化的要求。而基于三维可视化的建筑信
息模型(BIM)技术可以对施工进度进行有效监控。本文首先对传统的配电网工程施工进度管理中存在的问题进行了分析，即计划粗放、现场
数据滞后、偏差分析依靠个人经验、参建各方配合差四个方面的问题，并阐述了 BIM 技术和进度动态管理之间的关系，在模型承载、信息
交互及可视化决策三个方面进行论述；然后提出了基于 BIM 的进度动态管理系统，包括 4D 进度模型的建模要求以及轻量化交付方式、计
划-模型-现场三者联动的进度监控方式、基于赢得值法和前锋线法的偏差分析手段、“预警-分析-纠正-再评价”的动态纠偏过程；最后从组
织上、制度上、技术上和数据上提出相应的实施方案。研究结果显示，基于 BIM 进行进度动态管理可以将进度偏差发现时间从每周减少到
每天，工期预报精度大幅提高，有利于配电网工程按期顺利投运。</p>
      </abstract>